CRBC reschedules $140 million of outstanding debt (principal arrears) with the Congolese Government in 2022 (Linked to Record ID#105739)


Funder China Road & Bridge Corporation (CRBC)
Recipient Organization Government of Republic of Congo
Country Congo
Start Date Jan 01, 2022
End Date Nov 30, 2027
Duration 2,159 days
Number of Grantees 1
Roles Recipient
Data Source AidData Chinese Aid
Grant ID 105740
Grant Description

The Congolese authorities first announced its intention to concession National Road 1 (RN1) and National Road 2 (RN2) on February 6, 2016.

La Congolaise des Routes S.A. [LCR or (刚果(布)国家1号公路特许经营项目公司] — a special purpose vehicle and joint venture between CSCEC (70% ownership stake), Egis Projects (15% ownership stake) and the Congolese Government (15% ownership stake) — passed the pre-qualification stage in June 2016 and submitted a technical and financial proposal in February 2017.

It then received a ‘priority negotiation invitation letter’ in November 2017. Negotiations between LCR and the Congolese Government took place between December 2017 and April 2018. The parties finalized and signed a 30-year concession (franchise) agreement at the FOCAC Summit in September 2018.

Then, on December 10, 2020, the Government of the Republic of Congo signed a supplier’s credit agreement with China Road and Bridge Corporation (CRBC) for the 835 km Brazzaville-Ouesso Section of the National Road 2 (RN2) Rehabilitation and Extension Project (captured in Record ID #105739).

📋 Loan / Grant Terms
💰 Loan Amountare unknown

However, it is known that CRBC and the Government of the Republic of Congo signed a debt rescheduling agreement in 2022, which rescheduled $140 million of outstanding debt (principal arrears) under the supplier’s credit agreement.

According to IMF Country Report No. 23/89, the rescheduling agreement provided for a ‘regularization of arrears with [CSCEC] which involved converting the original CFA franc debt into U.S. dollars […].’ The same report notes that the arrangement was subsequently ‘unwound—corrected by reconverting the debt back into CFA francs.’

📋 Staff Comments
  1. The French project title is Travaux d’urgence sur la Route Nationale n°2 à partir du rond-point Mikalou jusqu’au pont Djiri et sur la 2ème sortie nord de Brazzaville y compris la Brettelle Ragec or Mikalou-Pont Djiri, longue de 14 km, y compris Bretelle Ragec, longue de 2,8 km.
  2. According to the World Bank’s International Debt Statistics (IDS), the Congolese Government had principal arrears to ‘private’ Chinese creditors worth $1,171,780,000 in 2021 and $49,802,000 in 2022 (see https://www.dropbox.com/scl/fi/g54lg0kqd2rg6tirlt59f/Principal-and-interest-arrears-of-ROC-to-Chinese-commercial-creditors-IDS-July-2024.xlsx?rlkey=rv0r2kfzw3reyyxl5ekpcl0b0&dl=0).
  3. According to the World Bank’s International Debt Statistics (IDS), the Congolese Government and its ‘private’ Chinese creditors rescheduled principal repayment obligations worth $1,146,879,000 in 2022 (see https://www.dropbox.com/scl/fi/shqo5w418nwvocuiibhn8/IDS-Principal-and-Interest-Amounts-Rescheduled-14-July-2024.xlsx?rlkey=6mka34nyg2qpwd7lvgfxz6x87&dl=0). $1,146,879,000 is roughly equivalent to the sum of the values of two debt treatments that are identified in the February 2023 World Bank-IMF Debt Sustainability Analysis for Congo-Brazzaville (https://documents1.worldbank.org/curated/en/099220503022313177/pdf/BOSIB08f099df703e0b0540dd698cc66f60.pdf) and the Congolese Ministry of Finance’s 2022 Public Debt Report (https://web.archive.org/web/20240605224117/https://www.finances.gouv.cg/sites/default/files/documents/Rapport%20sur%20la%20dette%202022%20V4.pdf): a $1 billion (CFA 450 billion) debt rescheduling with China State Construction Engineering Corporation (CSCEC) and a $140 million debt rescheduling with China Road and Bridge Corporation (CRBC).
  4. The concession agreement can be accessed in its entirety via https://www.sgg.cg/JO/2019/congo-jo-2019-01-sp.pdf.”
📚 Sources & References
  • Bulletin statistique de la dette publique
  • Congo/Chine : La Chine, amie de Sassou Nguesso ou amie du Peuple congolais ?
  • Des entreprises chinoises réaffectent le remboursement de leurs créances dans de nouveaux projets au Congo
  • Djiri : démarrage des travaux de réhabilitation de la route de l’Académie militaire
  • Documentation
  • IDS Principal and Interest Amounts Rescheduled 14 July 2024
  • IMF Country Reports - Republic of Congo: 2021 Article IV Consultation-Press Release; Staff Report; and Statement by the Executive Director for the Republic of Congo
  • Infrastructures : trois sociétés chinoises réinjectent leurs créances dans de nouveaux chantiers
  • JOURNAL OFFICIEL DE LA REPUBLIQUE DU CONGO paraissant le jeudi de chaque semaine à Brazzaville
  • Partenariat public-privé : Signature d’actes d’engagement pour la relance de l’économie
  • Principal and interest arrears of ROC to Chinese commercial creditors IDS July 2024
  • Rapport N°92 de la Commission Economie et Finances Relatif au Debat d'Orientation Budgetaire
  • RAPPORT SUR LA DETTE 2022
  • REPUBLIC OF CONGO FOURTH REVIEW UNDER THE THREE-YEAR ARRANGEMENT UNDER THE EXTENDED CREDIT FACILITY
  • REQUESTS FOR MODIFICATION OF PERFORMANCE CRITERIA
  • WAIVERS OF NONOBSERVANCE OF PERFORMANCE CRITERIA
  • AND FINANCING ASSURANCES REVIEW—PRESS RELEASE; STAFF REPORT; DEBT SUSTAINABILITY ANALYSIS; SUPPLEMENTARY INFORMATION; AND STATEMENT BY THE EXECUTIVE DIRECTOR
  • Republic of Congo Joint World Bank-IMF Debt Sustainability Analysis
  • REQUEST FOR A THREE-YEAR ARRANGEMENT UNDER THE EXTED CREDIT FACILITY—PRESS RELEASE; STAFF REPORT; AND STATEMENT BY THE EXECUTIVE DIRECTOR FOR THE REPUBLIC OF CONGO
  • RN2 : Jean Jacques Bouya optimiste
  • Route nationale n°2 : le tronçon Djiri-Ingah en pleine réhabilitation
  • Signature d’un acte d’engagement pour la réalisation des projets dans les domaines agricole et d’infrastructures
  • Strategie de destion de la dette à moyen-terme
  • Transport : lancement de la concession des routes nationales I et II
  • Trois sociétés chinoises s’engagent à relancer les projets au Congo _ Ministry of Development Territorial Equipment and Major Works
  • UN General Assembly National report submitted pursuant to Human Rights Council resolutions 5/1 and 16/21* Congo
  • 刚果(布)2号公路涵洞修复工程及金德磊大学城水毁工程通过最终验收 Loan applications and disbursements are still being received and processed as the projects continue to evolve. Ongoing monitoring and evaluation are in place to ensure project continuity.
All Grantees

Government of Republic of Congo

Advertisement
Apply for grants with GrantFunds
Advertisement
Browse Grants on GrantFunds
Interested in applying for this grant?

Complete our application form to express your interest and we'll guide you through the process.

Apply for This Grant