Completed PROJECT GRANT Swedish Research Council

Digitalisation for reduced idle loads in the food industry

4.01M kr SEK

Funder Vinnova
Recipient Organization Unknown
Country Sweden
Start Date Nov 30, 2022
End Date Nov 10, 2023
Duration 345 days
Number of Grantees 1
Roles Principal Investigator
Data Source Swedish Research Council
Grant ID 2022-03270_Vinnova
Grant Description

Purpose and goal: The project Kronägg carried out includes construction of an integrated control with

operational monitoring to control the use of electricity according to prevailing needs through automatization, make the systems flaws visible and reduce idle loads. Kronägg has installed an overall control system, connecting property systems with process and support systems were these work together to adapt to prevailing operating.

Kronägg has connected four processes during 9 months 2023 which then is need-based, we are in the beginning of performance measurement but already see big savings. Expected results and effects: ** Denna text är maskinöversatt **

Kronägg sees results after the first nine months of the year and the reduction in energy is significantly greater than we hoped for. Kronägg has saved 250 MWh during the installation period despite increased production during the same time.

Kronägg looks forward to the post-report in 2024 when all processes and control systems have delivered during the whole time.

It is great to see the interest from our technicians in this project and we look forward seeing more innovative solutions in the future. Approach and implementation:

Construction boundary has been done in dialogue with service partners for Kronägg. Implementation of the electricity-saving measures has been prioritized, which has resulted in rapid savings. The project parties have deliberately allowed it to take time to implement a new SCADA solution as it requires more time to collection data to fine-tune settings and achieve energy savings combined with IT security.

Future proofing and consensus within the group regarding the chosen solution are essential to provide the springboard and foundation that Kronägg is seeking for its digitization journey.

All Grantees

Unknown

Advertisement
Discover thousands of grant opportunities
Advertisement
Browse Grants on GrantFunds
Interested in applying for this grant?

Complete our application form to express your interest and we'll guide you through the process.

Apply for This Grant