Loading…
Loading grant details…
| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Sierra Leone Ministry of Finance and Economic Development |
| Country | Sierra Leone |
| Start Date | Aug 26, 2019 |
| End Date | Aug 18, 2028 |
| Duration | 3,280 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 62458 |
China Eximbank provides RMB 207 million government concessional loan for Phase 2 of National Fibre Optic Backbone Infrastructure Project On June 23, 2019, the Chinese Government and the Government of Sierra Leone signed a preferential loan framework agreement for Phase 2 of the National Fibre Optic Backbone Infrastructure Project.
Then, on August 26, 2019, China Eximbank and the the Government of Sierra Leone’s Ministry of Finance signed an RMB 207,000,000 government concessional loan (GCL) agreement [CHINA EXIMBANK GCL NO (2019) 10 TOTAL No. (681)] for Phase 2 of the National Fibre Optic Backbone Infrastructure Project. The GCL agreement was then ratified by Sierra Leone’s Parliament on September 19, 2019.
The borrower is responsible for repaying the loan between 2024 and 2039. It also agreed to deposit project-related revenues in a special account to facilitate repayment.
Under the terms of the loan agreement, Government of Sierra Leone’s Ministry of Finance is also responsible for on-lending the proceeds of the GCL to a state-owned enterprise in Sierra Leone known as Sierra Leone Cable Company Limited (SALCAB).
SALCAB, in turn, is expected to use the proceeds of the GCL to finance a $30 million commercial contract (ID#0002881900010V) between the Government of Sierra Leone’s Ministry of Information and Communications and Huawei Technologies Co., Ltd., which was signed on April 11, 2019. SALCAB signed an on-lending agreement with the Ministry of Finance on August 22, 2019.
Under the original terms of the loan agreement, the borrower was responsible for making 30, equal, semi-annual principal payments. Loan disbursements amounted to $17,733,000 in calendar year 2020 and $11,700,100 in calendar year 2021.
The (principal) amount outstanding under the loan was $0 as of December 31, 2019, $17,733,000 as of December 31, 2020, $29,433,100 as of December 31, 2021, and $29,433,100 as of December 31, 2022.
According to official records, a disbursement of USD 6,000,000 was planned for 2023 and another USD 6,000,000 was planned for 2024.
The purpose of the project is to lay a 721.5-kilometer fiber-optic network that covers 15 major cities in the northern, eastern and southern regions of Sierra Leone.
Upon completion, the telecommunications infrastructure is expected to allow telecommunications operators to offer 3G and 4G services. Huawei Technologies Co., Ltd. is the EPC contractor responsible for implementation. On April 24, 2020, the Government of Sierra Leone received the relevant technical equipment for project implementation.
By September 2020, construction had commenced.
Then, on September 28, 2020, Sierra Leone’s Ministry of Information and Communications and Sierra Leone Cable Limited (SALCAB) carried out an inspection visit to a project site in Moyamba. The delegation also inspected the work in progress along the Mano Junction-Daru axis.
The technical implementation of the work involves digging the path where the fiber cables will be laid, deploying the fiber ducts, backfilling the path and finally blowing the fiber through the duct. The work along this axis was approximately 50% complete in September 2020. The second phase of the network is expected to reach completion within two years.
Once the project’s civil work are completed, the next step will be the installation of other equipment and the introduction of fiber optic cables inside the high definition power pipes.
From February 21 to March 2, 2023 a technical team from Sierra Leone's Ministry of Information and Communications dispatched a team to monitor and evaluate the project's implementation. They were told by the contractors that the project was in its final stages of completion. Around August 21, 2023, Huawei officially handed the completed National Fibre Backbone project over to LeoneCom.
The connectivity and communication infrastructure for 14 out of 16 districts in Sierra Leone were enhanced.
Sierra Leone Ministry of Finance and Economic Development
Complete our application form to express your interest and we'll guide you through the process.
Apply for This Grant