CDB provides $12.3 million loan for 110kv Akpoga Electricity Infrastructure Project On January 22, 2019, the Hubei Branch of China Development Bank (CDB) and the Government of Equatorial Guinea signed an EUR 200 sovereign credit cooperation agreement (captured via Record ID#62258).
CDB subsequently approved a $12,331,205 loan for the 110kv Akpoga Electricity Infrastructure Project (captured via Record ID#87016).
According to Caja Autónoma de Amortización de la Deuda Pública within Equatorial Guinea’s Ministry of Finance and Budget, this loan had fully disbursed as of December 31, 2019 but the borrower had not made any principal or interest repayments as of December 31, 2019.
The purpose of the project was to construct a 110kv transmission line and substation at the Akoga (Akpoga) cement factory in the town of Akelayong within Kogo District (near Equatorial Guinea's border with Gabon). CMEC was the EPC contractor responsible for implementation. On July 10, 2017, the substation component of the project was completed and a handover ceremony took place