| Funder | Industrial and Commercial Bank of China (ICBC) |
|---|---|
| Recipient Organization | CCA Green B S.A. |
| Country | Argentina |
| Start Date | Apr 29, 2019 |
| End Date | Sep 20, 2026 |
| Duration | 2,701 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 92369 |
BOC and ICBC's contributions to National Road Line B (Corredor B Toll Road) On July 26, 2018, the Argentine National Road Agency and CCA Green B S.A. — a special purpose vehicle jointly owned by China Construction America (CCA) Inc. and Green SA (a local Argentinian firm) — signed a $2.13 billion franchise (concession) agreement for the National Road Line B (Corredor B Toll Road) Project.
Under the terms of the agreement, CCA Green B S.A. assumed responsibility for constructing a 538 km Corredor B toll road over a five year period and operating the road for 10-years after the end of the construction period.
Then, on April 25, 2019, CCA Green B S.A. signed $1.18 billion syndicated loan agreement with Bank of China, the Industrial and Commercial Bank of China (ICBC), HSBC, Santander, and Sumitomo Mitsui Banking Corporation (SMBC). ICBC's estimated contribution is captured via Record ID#92369. Bank of China's estimated contribution is captured via Record ID#54738.
The borrower also purchased a credit insurance policy from Sinosure.
The proceeds of the loan were to be used by the borrower to finance an EPC contract with China State Construction Engineering Corporation (CSCEC).
The purpose of the 538 km National Road Line B (Corredor B Toll Road), which is being financed and implemented on a Public-Private Partnership (PPP) basis, is to convert two sections (113 km and 31 km) of National Route 5 into a highway and convert another 372 km section into a safe highway.
National Route 5 passes through the provinces of Buenos Aires and La Pampa, which are two important industrial and agricultural economic zones in Argentina.
After the completion of the project, the vehicle traveling speed at this road section is expected increase to 130km/h and the road will be widened to a two-way four-lane road.
The highway is also expect top play a key role in accelerating economic growth in the region by effectively contributing to the government’s tax revenue, creating employment opportunities and boosting the development of relevant industries. On December 6, 2018, a project commencement ceremony took place in Suipacha, Buenos Aires.
Then, in January 2019, the former Argentine President Mauricio Macri and the governor of Buenos Aires, María Eugenia Vidal, visited the province of Buenos Aires Suipacha and inspected the project site. However, the project encountered various implementation obstacles in 2019 and 2020. In September 2019, a contractual dispute between CCA and Green SA was taken to the International Court of Arbitration.
Then, in early 2020, Argentina’s Public Works Minister Gabriel Katopodis announced that 5 of 6 PPP contracts were terminated (referring to them as "a ruinous model”). These contractual issues led to major work stoppages.
In December 2020, the Government of Argentina announced that it had agreed to terminate the final PPP contract, which was the agreement with CCA Green B S.A. There was no evidence of loan disbursements or physical progress at the time of cancellation.