| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Belarus Ministry of Finance |
| Country | Belarus |
| Start Date | Aug 27, 2021 |
| End Date | Sep 16, 2027 |
| Duration | 2,211 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 92533 |
China Eximbank provides $19.55 million preferential buyer’s credit for 220kV Stolbtsy Substation Reconstruction and 330kV Stolbtsy-Baranovichi Transmission Line Construction Project On August 27, 2021, China Eximbank and the Ministry of Finance of the Republic of Belarus signed a $19.55 million preferential buyer’s credit (PBC) agreement [CHINA EXIMBANK PBC NO. (2021) 1 TOTAL NO. (508)] for the 220kV Stolbtsy Substation Reconstruction and 330kV Stolbtsy-Baranovichi Transmission Line Construction Project.
The proceeds of the PBC are to be used by the borrower to partially finance a commercial contract with North China Power Engineering Co., Ltd. (NCPE).
The purpose of the project is to reconstruct the 220kV Stolbtsy (Столбцы) substation and construct a 330kV transmission line that runs from the Stolbtsy (Столбцы) substation to the Baranovichi (Барановичи) substation. The ultimate objective of the project is to evacuate power from the Belarusian Nuclear Power Plant (BNPP).
NCPE — a subsidiary of China Power Engineering Consulting Group — is the EPC contractor responsible for implementation.