| Funder | Industrial and Commercial Bank of China (ICBC) |
|---|---|
| Recipient Organization | Sihanoukville Special Economic Zone Thermal Power Company Limited (西港特区热电有限公司) |
| Country | Cambodia |
| Start Date | Jun 28, 2021 |
| End Date | Dec 25, 2031 |
| Duration | 3,832 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 92546 |
ICBC and BOC contribute to syndicated RMB and USD loans of unknown value for 100MW Sihanoukville SEZ Coal-Fired Power Plant Project On June 28, 2021, the Industrial and Commercial Bank of China (ICBC) (captured via Record ID#92546) and the Jiangsu Branch of Bank of China (captured via Record ID#92547) signed an RMB-denominated syndicated buyer’s credit loan and a USD-denominated syndicated buyer’s credit loan with Sihanoukville Special Economic Zone Thermal Power Company Limited (西港特区热电有限公司) — a special purpose vehicle and wholly-owned subsidiary of Sihanoukville Special Economic Zone Company Limited that was created in 2018 — for the 100MW Sihanoukville Special Economic Zone (SEZ) Coal-Fired Power Plant Project.
Neither the face values nor the borrowing terms of these loans are known.
In June 2021, Sinosure's Jiangsu Branch also issued an export buyer's credit insurance policy, and the project achieved financial closure.
The purpose of the project is to construct a 100 MW coal-fired power plant — with two 50 MW generators — in Sihanoukville Special Economic Zone (SEZ) within Prey Nob District and Preah Sihanouk Province (exact locational coordinates: 10.62902, 103.63363).
Zhejiang Gas & Thermoelectricity Design Institute Company Limited (浙江城建煤气热电设计院有限公司) is the contractor responsible for the project design.
Wuxi Guolian Huaguang Electric Power Engineering Company Limited (无锡国联华光电站工程有限公司) is the contractor responsible for project implementation. The project officially commenced on May 31, 2019.
The project’s first phase was initially expected to be ready for initial trial in October 2020 but it was delayed by the COVID-19 pandemic. The first-generation unit was connected to the grid and put into operation on July 1, 2021.
The inauguration ceremony for the project was attended by Cambodian and Chinese officials, including the Vice-Head of the United Front Work Department of the Central Committee of the Chinese Communist Party and the SEZ developer and contractor.
Sihanoukville Special Economic Zone Thermal Power Company Limited (西港特区热电有限公司)