Loading…

Loading grant details…

Active Mixed AidData Chinese Aid

China Eximbank provides $79.9 million loan for Kafue Bulk Water Supply Power Substations Project (Linked to Record ID#53038)

$79.98M USD

Funder Export-Import Bank of China (China Eximbank)
Recipient Organization Zambia Ministry of Water Development, Sanitation and Environmental Protection
Country Zambia
Start Date Jan 01, 2019
End Date Jan 27, 2033
Duration 5,140 days
Number of Grantees 1
Roles Recipient
Data Source AidData Chinese Aid
Grant ID 98552
Grant Description

China Eximbank provides $79.9 million loan for Kafue Bulk Water Supply Power Substations Project In May 2016, China Eximbank and the Government of Zambia signed a $127.5 million preferential buyer's credit (PBC) agreement for the Phase I of Lusaka-Kafue Bulk Water Supply Project (as captured via Record ID#53038).

The borrowing terms of the PBC are unknown.

However, it is known that the borrower was expected to use the proceeds from the PBC to finance 85% of a $150 million commercial contract between Lusaka Water and Sewerage Company (LWSC) and China Civil Engineering Construction Corporation (CCECC) Zambia Limited, which was signed in January 2013. The Government of Zambia agreed to directly finance the remaining 15% ($22.5 million) of the commercial contract cost.

The project involved the construction of a new raw water abstraction station on the Kafue River, a water treatment plant, a 66 km treated water pipeline from Kafue to Lusaka, and a booster station in Chilanga and transmission lines to deliver a total of 50,000m3/day of water into the existing Stuart Park storage facilities in Lusaka.

The ultimate objective of the project was to improve water supply to Lusaka and surrounding areas. Upon completion, the project was expected to benefit 480,000 people in Lusaka and surrounding areas.

China Civil Engineering Construction Corporation (CCECC) Zambia Limited was the EPC contractor responsible for project implementation. Its work was overseen by Lusaka Water and Sewerage Company (LWSC). A formal groundbreaking ceremony took place on July 20, 2016. However, construction did not begin until September 5, 2016.

It was originally anticipated that the project would be completed by November 2018. However, this did not occur due to delays in the delivery of water distribution pipelines.

The scope of the project was also revised during implementation to include additional works involving the construction of the Iolanda intake structure (at the Iolanda water treatment plant) and the installation of the Chilanga Booster Pump to meet the power requirements of the project.

On September 17, 2020, the President of Zambia visited the project site and affirmed the construction quality and progress of the project. As of December 2020, the project had achieved a 96% completion rate. On July 29, 2022, a project completion ceremony took place.

At the ceremony, Zambian president Hakainde Hichilema said that the completion of the project would ensure that about 500,000 people in the Zambian capital have access to clean and safe water as well as proper sanitation.

Eric Ding, the general manager of the CCECC Zambia, thanked the Zambian government and the local people for their support during the construction period.

He, however, said more financing will be required to undertake the second phase of the project to increase the water supply to the Zambian capital due to the increased population which requires more water. 1,000 local residents were reportedly employed and trained at the peak of the construction phase of the project.

China Eximbank and Zambia’s Ministry of Water Development, Sanitation, and Environmental Protection also signed a $79,982,494.00 term loan facility agreement for the Kafue Bulk Water Supply Power Substations Project circa 2019.

📋 Loan / Grant Terms
💰 Loan Amountare unknown

The purpose of the project is to construct electricity substations (transformers) and additional works to support the newly constructed facilities at the Kafue Bulk Water Supply Project. The electricity substations were originally scheduled for installation by February 2020. However, they were not delivered on time for unspecified reasons.

📋 Staff Comments
  1. This loan is not included in the SAIS-CARI database of Chinese loan commitments that was released in 2020 and re-released in 2021.
  2. The precise loan commitment date is unknown. For the time being, AidData assumes that the loan agreement was finalized in 2019 (one year before the substations were expected to be installed). However, this issue requires further investigation.
  3. For the time being, AidData assumes that the same estimated borrowing terms that applied to the China Eximbank PBC that supported Phase I of the Lusaka-Kafue Bulk Water Supply Project (16.0126-year maturity, 4.3254-year grace period, and 3.4612% interest rate) also applied to the China Eximbank PBC for the Kafue Bulk Water Supply Power Substations Project. This issue warrants further investigation.
📚 Sources & References
  • Project Financing
  • REPORT OF THE COMMITTEE ON GOVERNMENT ASSURANCES FOR THE FOURTH SESSION OF THE TWELFTH NATIONAL ASSEMBLY
  • BULK WATER CONTRACTOR URGED TO COMPLETE PROJECT BY JUNE, $150 MILLION KAFUE BULK WATER PROJECT 100% COMPLETE
  • KAFUE BULK WATER PROJECT TRANSFORMERS IN Lusaka Water Supply and Sanitation Company has received transformers to power the soon to be launched Kafue Bulk Water Project.
  • OPERATIONALISE KAFUE BULK WATER
  • REPORT OF THE COMMITTEE ON GOVERNMENT ASSURANCES FOR THE FIFTH SESSION OF THE TWELFTH NATIONAL ASSEMBLY
  • Water shortage resolved next month Loan applications and disbursements are still being received and processed as the projects continue to evolve. Ongoing monitoring and evaluation are in place to ensure project continuity.
All Grantees

Zambia Ministry of Water Development, Sanitation and Environmental Protection

Advertisement
Discover thousands of grant opportunities
Advertisement
Browse Grants on GrantFunds
Interested in applying for this grant?

Complete our application form to express your interest and we'll guide you through the process.

Apply for This Grant